Enquire

Construction
Update

22 July 2021

• Roof works complete
• External paintwork and finishes progressing
• Ceiling and wall finishing trades up to level 4 and level 5
• Fit-off of plumbing and electrical trades continuing
• Tiling to bathrooms and ensuites advanced
• Cabinetwork now progressing through level 3
• Stone benchtops and splashbacks installed to ground and level 1
• Scaffold to exterior starting to be removed
• External works to pavilion and pool area well underway. Concrete pool shell complete.

22 April 2021 Topping out event by PACT

Upcoming works for the next month include:
• Roof structure complete;
• Roof cover and roof plumbing nearing completion;
• Stud framing well advanced level 4 and commencing level 5;
• Plasterboard linings and skim soffits following framing;
• Window frame installation and glazing progressing;
• Service reticulation moving with stud framing;
• Waterproofing to balconies and wet areas well advanced; and
• Internal tiling progressing.

25 March 2021 Topped out!

Upcoming works for the next month include:
• Topped out;
• Roof steel advanced;
• Stud framing complete ground to level 2 and progressing on level 3;
• Plasterboard linings and skim soffits following framing;
• Window frame installation progressing; and
• Service reticulation moving with stud framing

15 March 2021 Levelling up!

• Level 3 suspended slab complete;
• Level 4 formwork commenced;
• Services prelays advancing with slabs
• Services reticulation well underway
• External window systems starting to be installed

19 February 2021 Levels are being completed

You can now see the beautiful view out on to Henderson park from the inside!

15 December 2020 Basement structure nearing completion

- Ground floor suspended slab well advanced;
- Level 1 suspended slab pour 1 complete;
- Scaffold to level 2 commenced; and
- Services progressing with structure.

24/11 Retaining walls advancing

-Bulk earthworks complete
-Basement retaining wall construction advancing
-Formwork and reinforcement install to first suspended slab progressing
-Services prelays progressing with slab pours

13/11 Progress

Walls are going up.

3/11 Concrete Pour

Concrete is being poured in the basement slab with footings installed.

16/10 Crane Installed

Dewatering for the crane base excavation is ongoing, complete the excavation for the crane base.

-Pour crane base concrete and install crane.
-Completed bulk earthworks.
-Install soak wells.
-Install formwork and are in preparation for concrete pour for basement lift pit, follow on with footings and basement slab, concrete pour programmed for mid-October.

More updates in the weeks to come!

25/09 PACT Appointed as Builder

We are absolutely thrilled to announce that PACT have commenced construction at One Mabel Park.

This week de watering was completed on-site preparing for works.

Within the next two weeks, we should see the following completed:
- Earthworks
- Concrete crane base
- Footings and the basement slab