Enquire

Construction
Update

October 2020 Construction Update

Dewatering for the crane base excavation is ongoing, complete the excavation for the crane base.

-Pour crane base concrete and install crane.
-Completed bulk earthworks.
-Install soakwells.
-Install formwork and are in preparation for concrete pour for basement lift pit, follow on with footings and basement slab, concrete pour programmed for mid-October.

More updates in the weeks to come!

September 2020 Construction Update

We are absolutely thrilled to announce that PACT have commenced construction at One Mabel Park.

This week de watering was completed on-site preparing for works.

Within the next two weeks, we should see the following completed:
- Earthworks
- Concrete crane base
- Footings and the basement slab

We look forward to keeping you up to date with the progress of construction.